Delivery forecast

Forecast when a backlog finishes from past weekly throughput, with a cautious date as well as the likely one.

Paste a few weeks of throughput and set the backlog.

The tool

Likely week (p50)
Safer week (p80)
Cautious week (p90)

How it's calculated

Each simulated week draws one past week at random, with the same seeded generator as the approval simulator. The percentiles are where half, 80% and 90% of those runs had finished the backlog.

When I use it

Averages promise a date the team will miss. Past weeks already contain the slow ones. This forecast samples those weeks, the same way the approval simulator samples response times, and reads the spread.

How I read it

p50 is the likely week. p80 is the date I put on a plan. p90 is what I say when someone asks for a promise. If p90 is far from p50, the history is uneven and the plan should say so.

The trap

A history of only good weeks makes the forecast cheerful. Include the slow weeks, or the date is a wish.